20th May 2012 Updation Schedule
External Painting Work in Progress






Internal Painting Work in Progress


1st & 2nd Floor Internal Painting Work Completed


1st & 2nd Floor Kitchen Work Completed


1st & 2nd Floor Switch Fixing Work Completed


3rd & 4th Floor Internal Painting Work Completed

3rd & 4th Floor Kitchen Sink Fixing Work in Progress


5th & 6th Floor Internal Painting Work in Progress


5th & 6th Floor Switch Fixing Work in Progress


7th & 8th Floor Internal Wall Putty Work Completed


7th & 8th Floor Kitchen Tiles Dadoing Work Completed


9th & 10th Floor Internal Painting Work in Progress


11th & 12th Floor Internal Wall Putty Work Completed


11th & 12th Floor Internal Door Fixing Work in Progress


13th & 14th Floor Internal Wall Putty Work Completed


15th & 16th Floor Internal Wall Putty Work in Progress


17th & 18th Floor Internal Wall Putty Work Completed


17th & 18th Floor Internal Flooring Work in Progress


19th Floor Internal Wall Putty Work in Progress


Over Head Water Tank Painting Work in Progress

5th May 2012 Updation Schedule
External Painting Work in Progress






Internal Painting Work in Progress


1st & 2nd Floor Internal Painting Work Completed


1st & 2nd Floor Kitchen Work Completed


3rd & 4th Floor Internal Painting Work Completed


3rd & 4th Floor Kitchen Work Completed


5th & 6th Floor Internal Painting Work in Progress


7th & 8th Floor Internal Wall Putty Work Completed


7th & 8th Floor Bathroom Tiles Dadoing Work Completed


9th & 10th Floor Internal Wall Putty Work Completed


9th & 10th Floor Kitchen Tiles Dadoing Work in Progress


11th & 12th Floor Internal Wall Putty Work Completed


13th & 14th Floor Internal Wall Putty Work Completed


13th & 14th Floor Internal Flooring Work in Progress


15th & 16th Floor Internal Wall Putty Work in Progress


15th & 16th Floor Bathroom Tiles Dadoing Work in Progress


17th & 18th Floor Internal Wall Putty Work in Progress


17th & 18th Floor Bathroom Tiles Dadoing Work in Progress


19th Floor Internal Plastering Work Completed


Over Head Water Tank Painting Work in Progress

20th April 2012 Updation Schedule
External Painting Work in Progress
/100.JPG)
/101.JPG)
/102.JPG)
/103.JPG)
/104.JPG)
Internal Painting Work in Progress
/200.JPG)
/201.JPG)
1st & 2nd Floor Internal Painting Work Completed
/300.JPG)
/301.JPG)
1st & 2nd Floor Bathroom Final Finishing Work in Progress
/400.JPG)
/401.JPG)
3rd & 4th Floor Internal Painting Work Completed
/500.JPG)
/501.JPG)
5th & 6th Floor Internal Painting Work Completed
/600.JPG)
/601.JPG)
7th & 8th Floor Internal Painting Work in Progress
/700.JPG)
/701.JPG)
9th & 10th Floor Internal Painting Work in Progress
/800.JPG)
/801.JPG)
9th & 10th Floor Kitchen Tiles Dadoing & Granite Fixing Work Completed
/900.JPG)
/901.JPG)
11th & 12th Floor Internal Wall Putty Work Completed
/1000.JPG)
/1001.JPG)
11th & 12th Floor Internal Flooring Work in Progress
/1200.JPG)
/1201.JPG)
13th & 14th Floor Internal Wall Putty Work Completed
/1300.JPG)
/1301.JPG)
15th & 16th Floor Internal Wall Putty Work Completed
/1400.JPG)
/1401.JPG)
15th & 16th Floor Internal Bathroom Tiles Dadoing Work in Progress
/1500.JPG)
/1501.JPG)
17th & 18th Floor Wall Putty Work Completed
/1600.JPG)
/1601.JPG)
17th & 18th Floor Internal Flooring Work in Progress
/1700.JPG)
/1701.JPG)
19th Floor Internal Plastering Work Completed
/1800.JPG)
/1801.JPG)
19th Floor Internal Flooring Work in Progress
/1900.JPG)
Over Head Water Tank Painting Work in Progress
/2000.JPG)
5th April 2012 Updation Schedule
External Painting Work in Progress





Internal Painting Work in Progress


5th & 6th Floor Internal Painting Work Completed


5th & 6th Floor Kitchen Granite Fixing Work Completed


7th & 8th Floor Internal Painting Work in Progress


7th & 8th Floor Internal Flooring Work in Progress


9th & 10th Floor Internal Wall Putty Work Completed


9th & 10th Floor Kitchen Tiles Dadoing & Granite Fixing Work Completed


11th & 12th Floor Internal Wall Putty Work Completed


11th & 12th Floor Bathroom Tiles Dadoing Work in Progress


13th & 14th Floor Internal Wall Putty Work Completed


13th & 14th Floor Kitchen Tiles Dadoing and Granite Fixing Work Completed

15th & 16th Floor Internal Wall Putty Work Completed


15th & 16th Floor Bathroom Tiles Dadoing Work in Progress


17th & 18th Floor Internal Wall Putty Work Completed


17th & 18th Floor Internal Flooring Work in Progress


19th Floor Internal Plastering Work Completed


19th Floor Internal Plumbing Work in Progress


Over Head Water Tank Painting Work in Progress

|