Confident Auriga
Project Progress Photos
 


15th January 2012 Updation Schedule

Phase - NRI - Road Concreting Work Completed

Phase - NRI - Site Marking Poles Fixing Work in Progress

Phase - NRI - Manual Chamber Plastering Work Completed

Phase - NRI - Individual Chamber Plastering Work Completed

Phase - NRI - Compound Wall Block Work Completed

Phase - KNSS - Road Concreting Work Completed

Phase - KNSS - Site Marking Poles Fixing Work in Progress

Phase - 3 - Road Concreting Work Completed

Phase - 3 - Individual Chamber Plastering Work Completed

Phase - 3 - Manual Chamber Plastering Work Completed

Phase - 3 - Drainage Block Work Completed

Phase - 3 - Compound Wall Block Work Completed

Phase - 9 - Road Concreting Work Completed

Phase - 9 - Site Marking Poles Fixing Work in Progress

Phase - 9 - Drainage Plastering Work in Progress

Phase - 9 - Manual Chamber Plastering Work Completed

Phase - 9 - Individual Chamber Plastering Work Completed

Phase - 9 - Compound Wall Block Work Completed


15th December 2011 Updation Schedule

Phase - NRI- Road Concreting Completed

Phase -NRI- Site Marking Pole Fixing Work in Progress

Phase - NRI- Drainage Plastering Work Completed

Phase - NRI- Individual Chamber Plastering Work Completed

Phase - NRI- Manual Chamber Plastering Work Completed

Phase - KNSS- Road Concreting Work Completed

Phase -KNSS- Site Marking Pole Fixing Work in Progress

Phase -KNSS- Compound Wall Block Work in Progress

Phase -VI- Road Concreting Work Completed

Phase -VI- Compound Wall Block Work in Progress

Phase -VI- Drainage Block Work Completed

Phase -VI- Drainage Plastering Work in Progress

Phase -VI- Site Marking Pole Fixing Work in Progress

Phase -VI- Manual Chamber Plastering Work Completed

Phase -IX- Road Concreting Work Completed

Phase -IX- 9'' Sanitary Pipe Line Earth Excavation Work in Progress

Phase - IX- Manual Chamber Plastering Work Completed

Phase - IX- Individual Chamber Plastering Work Completed

Phase -IX-  Drainage Block Work Completed

Phase -IX- Compound Wall Block Work Completed


15th November 2011 Updation Schedule

Phase - NRI- Road Concreting Work Completed

Phase - NRI- Site Marking Pole Installation Work in Progress

Phase - NRI- Manual Chamber Plastering Work Completed

Phase - NRI- Individual Chamber Plastering Work in Progress

Phase - NRI- Compound Wall Block Work in Progress

Phase - NRI- 9'' Sanitary Pipe Line Earth Excavation Work in Progress

Phase - NRI- Drainage Earth Excavation Work in Progress

Phase - KNSS- Road Concreting Work Completed

Phase - KNSS- Site Marking Pole Installation Work Completed

Phase - KNSS- 9'' Sanitary Pipe Line Earth Excavation Work in Progress

Phase - 6 - Road Concreting Work Completed

Phase - 6 - Site Marking Pole Installation Work Completed

Phase - 6 - Individual Chamber Plastering Work in Progress

Phase - 6 - Individual Chamber Block Work in Progress

Phase - 6 - 9'' Sanitary Pipe Line Earth Excavation Work in Progress

Phase - 6 - Drainage Block Work in Progress

Phase - 6 - Drainage Plastering Work in Progress

Phase - 9 - Road Concreting Work Completed

Phase - 9 - Compound Wall Block Work Completed

Phase - 9 - Drainage Block Work in Progress

Phase - 9 - Individual Chamber Plastering Work in Progress



   