20th May 2012 Updation Schedule
Block -A- External Painting Work in Progress


Block -A-1st & 2nd Floor Internal Painting Work Completed


Block -A-1st & 2nd Floor Kitchen Work Completed


Block -A- 3rd & 4th Floor Internal Painting Work Completed


Block -A- 3rd & 4th Floor Kitchen Work Completed


Block -A- Roof Parapet Plastering Work Completed

Block -A- Over Head Water Tank Painting Work in Progress

Block -C- External Painting Work in Progress


Block -C- 1st & 2nd Floor Internal Wall Putty Work in Progress


Block -C- 1st & 2nd Floor Internal Plumbing Work in Progress


Block -C- 3rd & 4th Floor Internal Plastering Work Completed


Block -C- 3rd & 4th Floor Internal Plumbing Work in Progress


Block -C- Roof Parapet Plastering Work Completed

Block -C- Over Head Water Tank Plastering Work Completed

Block -D- External Painting Work in Progress



Block -D- 1st & 2nd Floor Corridor Flooring Work in Progress


Block -D- 1st & 2nd Floor Internal Painting Work in Progress


Block -D- 3rd & 4th Floor Internal Wall Putty Work Completed


Block -D- 3rd & 4th Floor Internal Flooring Work in Progress


Block -D- Roof Parapet Plastering Work Completed

Block -D- Over Head Water Tank Painting Work in Progress

Block -E- External Painting Work in Progress



Block -E- 1st & 2nd Floor Corridor Painting Work in Progress


Block -E- 1st & 2nd Floor Internal Painting Work in Progress


Block -E- 1st & 2nd Floor Kitchen Painting Work in Progress


Block -E- 3rd & 4th Floor Internal Wall Putty Work Completed


Block -E- 3rd & 4th Floor Internal Flooring Work Completed


Block -E- Roof Parapet Painting Work in Progress

Block -E- Over Head Water Tank Plastering Work Completed

Block -F- External Painting Work in Progress


Block -F- 1st & 2nd Floor Corridor Work in Progress


Block -F- 1st & 2nd Floor Internal Painting Work in Progress


Block -F- 3rd & 4th Floor Internal Flooring Work Completed


Block -F- 3rd & 4th Floor Internal Painting Work in Progress

Block -F- Roof Parapet Painting Work in Progress

Block -F- Over Head Water Tank Painting Work in Progress

5th May 2012 Updation Schedule
Block -A- External Painting Work in Progress
 (Bangalore)05.05.2012/100.JPG)
 (Bangalore)05.05.2012/101.JPG)
Block -A- Elevator Work in Progress
 (Bangalore)05.05.2012/200.JPG)
Block -A- 1st & 2nd Floor Internal Painting Work Completed
 (Bangalore)05.05.2012/300.JPG)
 (Bangalore)05.05.2012/301.JPG)
Block -A- 1st & 2nd Floor Kitchen Work Completed
 (Bangalore)05.05.2012/400.JPG)
 (Bangalore)05.05.2012/401.JPG)
Block -A- 3rd & 4th Floor Internal Painting Work Completed
 (Bangalore)05.05.2012/500.JPG)
 (Bangalore)05.05.2012/501.JPG)
Block -A- 3rd & 4th Floor Bathroom Work Completed
 (Bangalore)05.05.2012/600.JPG)
 (Bangalore)05.05.2012/601.JPG)
Block -A- Roof Parapet Plastering Work Completed
 (Bangalore)05.05.2012/700.JPG)
Block -A- Over Head Water Tank Painting Work in Progress
 (Bangalore)05.05.2012/800.JPG)
Block -C- External Painting Work in Progress
 (Bangalore)05.05.2012/900.JPG)
 (Bangalore)05.05.2012/901.JPG)
Block -C- 1st & 2nd Floor Railing Work Completed
 (Bangalore)05.05.2012/1000.JPG)
 (Bangalore)05.05.2012/1001.JPG)
Block -C- 1st & 2nd Floor Internal Wall Putty Work in Progress
 (Bangalore)05.05.2012/1100.JPG)
 (Bangalore)05.05.2012/1101.JPG)
Block -C- 1st & 2nd Floor Internal Plumbing Work in Progress
 (Bangalore)05.05.2012/1200.JPG)
 (Bangalore)05.05.2012/1201.JPG)
Block -C- 3rd & 4th Floor Railing Work in Progress
 (Bangalore)05.05.2012/1300.JPG)
 (Bangalore)05.05.2012/1301.JPG)
Block -C- 3rd & 4th Floor Internal Wall Putty Work in Progress
 (Bangalore)05.05.2012/1400.JPG)
 (Bangalore)05.05.2012/1401.JPG)
Block -C- 3rd & 4th Floor Internal Plumbing Work in Progress
 (Bangalore)05.05.2012/1500.JPG)
 (Bangalore)05.05.2012/1501.JPG)
Block -C- Roof Parapet Plastering Work Completed
 (Bangalore)05.05.2012/1600.JPG)
Block -C- Over Head Water Tank Plastering Work in Progress
 (Bangalore)05.05.2012/1700.JPG)
Block -D- External Painting Work in Progress
 (Bangalore) for Update as on 05.05.2012/1800.JPG)
 (Bangalore) for Update as on 05.05.2012/1801.JPG)
 (Bangalore) for Update as on 05.05.2012/1802.JPG)
Block -D- 1st & 2nd Floor Internal Wall Putty Work Completed
 (Bangalore) for Update as on 05.05.2012/2000.JPG)
 (Bangalore) for Update as on 05.05.2012/2001.JPG)
Block -D- 1st & 2nd Floor Internal Flooring Work Completed
 (Bangalore) for Update as on 05.05.2012/2100.JPG)
 (Bangalore) for Update as on 05.05.2012/2101.JPG)
Block -D- 3rd & 4th Floor Internal Wall Putty Work Completed
 (Bangalore) for Update as on 05.05.2012/2200.JPG)
 (Bangalore) for Update as on 05.05.2012/2201.JPG)
Block -D- 3rd & 4th Floor Internal Flooring Work Completed
 (Bangalore) for Update as on 05.05.2012/2300.JPG)
 (Bangalore) for Update as on 05.05.2012/2301.JPG)
Block -D- 3rd & 4th Floor Bathroom Tiles Dadoing Work in Progress
 (Bangalore) for Update as on 05.05.2012/2400.JPG)
 (Bangalore) for Update as on 05.05.2012/2401.JPG)
Block -D- Roof Parapet Plastering Work Completed
 (Bangalore) for Update as on 05.05.2012/2500.JPG)
Block -D- Over Head Water Tank Painting Work in Progress
 (Bangalore) for Update as on 05.05.2012/2600.JPG)
Block -E- External Painting Work In Progress
 (Bangalore) for Update as on 05.05.2012/2700.JPG)
 (Bangalore) for Update as on 05.05.2012/2701.JPG)
Block -E- 1st & 2nd Floor Corridor Painting Work Completed
 (Bangalore) for Update as on 05.05.2012/2800.JPG)
 (Bangalore) for Update as on 05.05.2012/2801.JPG)
Block -E- 1st & 2nd Floor Internal Wall Putty Work Completed
 (Bangalore) for Update as on 05.05.2012/2900.JPG)
 (Bangalore) for Update as on 05.05.2012/2901.JPG)
Block -E- 1st & 2nd Floor Shutter Door Fixing Work Completed
 (Bangalore) for Update as on 05.05.2012/3000.JPG)
 (Bangalore) for Update as on 05.05.2012/3001.JPG)
Block -E- 3rd & 4th Floor Internal Wall Putty Work Completed
 (Bangalore) for Update as on 05.05.2012/3100.JPG)
 (Bangalore) for Update as on 05.05.2012/3101.JPG)
Block -E- 3rd & 4th Floor Kitchen Tiles Dadoing & Sink Fixing Work in Progress
 (Bangalore) for Update as on 05.05.2012/3200.JPG)
 (Bangalore) for Update as on 05.05.2012/3201.JPG)
Block -E- Roof Parapet Painting Work in Progress
 (Bangalore) for Update as on 05.05.2012/3300.JPG)
Block -E- Over Head Water Tank Plastering Work Completed
 (Bangalore) for Update as on 05.05.2012/3400.JPG)
Block -F- External Painting Work in Progress
 (Bangalore) for Update as on 05.05.2012/3500.JPG)
 (Bangalore) for Update as on 05.05.2012/3501.JPG)
Block -F- 1st & 2nd Floor Internal Wall Putty Work Completed
 (Bangalore) for Update as on 05.05.2012/3600.JPG)
 (Bangalore) for Update as on 05.05.2012/3601.JPG)
Block -F- 1st & 2nd Floor Bathroom Tiles Dadoing Work Completed
 (Bangalore) for Update as on 05.05.2012/3700.JPG)
 (Bangalore) for Update as on 05.05.2012/3701.JPG)
Block -F- 3rd & 4th Floor Wall Putty Work Completed
 (Bangalore) for Update as on 05.05.2012/3800.JPG)
 (Bangalore) for Update as on 05.05.2012/3801.JPG)
Block -F- 3rd & 4th Floor Internal Flooring Work Completed
 (Bangalore) for Update as on 05.05.2012/3900.JPG)
 (Bangalore) for Update as on 05.05.2012/3901.JPG)
Block -F- Roof Parapet Painting Work in Progress
 (Bangalore) for Update as on 05.05.2012/4000.JPG)
Block -F- Over Head Water Tank Painting Work in Progress
 (Bangalore) for Update as on 05.05.2012/4100.JPG)
20th April 2012 Updation Schedule
Block -A- External Painting Work in Progress
/100.JPG)
/101.JPG)
Block -A- Elevator Work in Progress
/200.JPG)
Block -A- 1st & 2nd Floor Internal Painting Work Completed
/300.JPG)
/301.JPG)
Block -A- 1st & 2nd Floor Kitchen Work Completed
/400.JPG)
/401.JPG)
Block -A- 3rd & 4th Floor Internal Painting Work Completed
/500.JPG)
/501.JPG)
Block -A- Roof Parapet Plastering Work Completed
/600.JPG)
Block -A- Over Head Water Tank Painting Work in Progress
/700.JPG)
Block -C- External Painting Work in Progress
/800.JPG)
/801.JPG)
Block -C- 1st & 2nd Floor Railing Work Completed
/900.JPG)
/901.JPG)
Block -C- 1st & 2nd Floor Wall Putty Work in Progress
/1000.JPG)
/1001.JPG)
Block -C- 3rd & 4th Floor Internal Plaster Work Completed
/1100.JPG)
/1101.JPG)
Block -C- Roof Parapet Plastering Work in Progress
/1200.JPG)
Block -C- Over Head Water Tank Plastering Work Completed
/1300.JPG)
Block -D- External Painting Work in Progress
/1400.JPG)
/1401.JPG)
/1402.JPG)
Block -D- 1st & 2nd Floor Internal Wall Putty Work Completed
/1500.JPG)
/1501.JPG)
Block -D- 1st & 2nd Floor Flooring Work Completed
/1600.JPG)
/1601.JPG)
Block -D- 1st & 2nd Floor Aluminum Door Fixing Work in Progress
/1700.JPG)
/1701.JPG)
Block -D- 3rd & 4th Floor Internal Wall Putty Work Completed
/1800.JPG)
/1801.JPG)
Block -D- 3rd & 4th Floor Internal Flooring Work in Progress
/1900.JPG)
/1901.JPG)
Block -D- Roof Parapet Plastering Work Completed
/2000.JPG)
Block -D- Over Head Water Tank Painting Work in Progress
/2100.JPG)
Block -E- External Painting Work in Progress
/2200.JPG)
/2201.JPG)
/2202.JPG)
Block -E- 1st & 2nd Floor Internal Wall Putty Work Completed
/2300.JPG)
/2301.JPG)
Block -E- 1st & 2nd Floor Kitchen Tiles Dadoing Work Completed
/2400.JPG)
/2401.JPG)
Block -E- 3rd & 4th Floor Internal Wall Putty Work Completed
/2500.JPG)
/2501.JPG)
Block -E- 3rd & 4th Floor Kitchen Tiles Dadoing Work in Progress
/2600.JPG)
/2601.JPG)
Block -E- Roof Parapet Painting Work in Progress
/2700.JPG)
Block -E- Over Head Water Tank Plastering Work Completed
/2800.JPG)
Block -F- External Painting Work in Progress
/2900.JPG)
Block -F- 1st & 2nd Floor Internal Wall Putty Work Completed
/3000.JPG)
/3001.JPG)
Block -F- 1st & 2nd Floor Kitchen Tiles Dadoing Work Completed
/3100.JPG)
/3101.JPG)
Block -F- 3rd & 4th Internal Wall Putty Work in Progress
/3200.JPG)
/3201.JPG)
Block -F- 3rd & 4th Floor Aluminum Shutter Door Fixing Work in Progress
/3300.JPG)
/3301.JPG)
Block -F- Roof Parapet Painting Work in Progress
/3400.JPG)
Block -F- Over Head Water Tank Work in Progress
/3500.JPG)
5th April 2012 Updation Schedule
Block -A- External Painting Work in Progress


Block -A- Corridor Painting Work in Progress

Block -A- 1st & 2nd Floor Internal Painting Work Completed


Block -A- 1st & 2nd Floor Kitchen Work Completed


Block -A- 3rd & 4th Floor Internal Painting Work in Progress


Block -A- 3rd & 4th Floor Internal Flooring Work in Progress


Block -A- Roof Parapet Plastering Work Completed

Block -A- Over Head Water Tank Painting Work in Progress

Block -C- External Plastering Work Completed




Block -C- 1st & 2nd Floor Railing Work Completed


Block -C- 1st & 2nd Floor Internal Wall Putty Work in Progress


Block -C- 3rd & 4th Floor Internal Plastering Work Completed


Block -C- Roof Parapet Plastering Work Completed

Block -C- Over Head Water Tank Plastering Work in Progress

Block -D- External Painting Work in Progress



Block -D- 1st & 2nd Floor Internal Wall Putty Work Completed


Block -D- 1st & 2nd Floor Bathroom Tiles Dadoing Work in Progress


Block -D- 3rd & 4th Floor Railing Work in Progress


Block -D- 3rd & 4th Floor Internal Wall Putty Work Completed


Block -D- 3rd & 4th Floor Internal Plumbing Work in Progress


Block -D- Roof Parapet Plastering Work Completed

Block -D- Over Head Water Tank Painting Work in Progress

Block -E- External Painting Work in Progress



Block -E- 1st & 2nd Floor Corridor Painting Work in Progress


Block -E- 1st & 2nd Floor Internal Wall Putty Work Completed


Block -E- 3rd & 4th Floor Corridor Painting Work in Progress


Block -E- 3rd & 4th Floor Internal Wall Putty Work Completed


Block -E- 3rd & 4th Floor Kitchen Granite Fixing Work in Progress


Block -E- Roof Parapet Painting Work in Progress

Block -E- Over Head Water Tank Plastering Work Completed

Block -F- External Painting Work in Progress

Block -F- 1st & 2nd Floor Internal Wall Putty Work Completed


Block -F- 1st & 2nd Floor Internal Flooring Work Completed


Block -F- 3rd & 4th Floor Internal Wall Putty Work Completed


Block -F- 3rd & 4th Floor Internal Flooring Work Completed


Block -F- Roof Parapet Painting Work in Progress

Block -F- Over Head Water Tank Painting Work in Progress
 |