20th May 2012 Updation Schedule
View of Entrance


Road Concreting Work Completed


Site Marking Poles Fixing Work in Progress


Compound Wall Painting Work Completed


View of Transformer

5th May 2012 Updation Schedule
ACP Cladding Work Completed


Road Concreting Work Completed


Site Marking Poles Fixing Work Completed



Individual Chamber Plastering Work Completed

Compound Wall Painting Work Completed


View of Transformer

20th April 2012 Updation Schedule
ACP Cladding Work Completed
/100.JPG)
/101.JPG)
Road Concreting Work Completed
/200.JPG)
/202.JPG)
/202.JPG)
/300.JPG)
/301.JPG)
/303.JPG)
Individual Chamber Plastering Work Completed
/400.JPG)
Compound Wall Painting Work Completed
/500.JPG)
/501.JPG)
5th April 2012 Updation Schedule
Main Gate ACP Cladding Work Completed


Road Concreting Work Completed



Site Marking Poles Fixing work Completed




Individual Chamber Plastering Work Completed

Compound Wall Painting Work Completed


View of Transformer

20th March 2012 Updation Schedule
Main Gate ACP Cladding Fixing Work Completed


Road Concreting Work Completed


Site Marking Poles Fixing Work Completed




Individual Chamber Plastering Work Completed

Compound Wall Painting Work Completed


View of Transformer

5th March 2012 Updation Schedule
Main Gate ACP Cladding Fixing Work in Progress


Road Concreting Work Completed




Site Marking Poles Fixing Work Completed




Individual Chamber Plastering Work Completed

Compound Wall Painting Work Completed


20th February 2012 Updation Schedule
Main Gate ACP Cladding Fixing Work in Progress


Road Concreting Work Completed



Site Marking Poles Fixing Work in Progress




Compound Wall Painting Work in Progress


|