5th February 2012 Updation Schedule
Phase - V - Road Concreting Work Completed



Phase - V - Site Marking Poles Fixing Work Completed




Phase - V - Compound Wall Painting Work in Progress

Phase - VI - Road Soling Work in Progress




Phase - VI - Manual Chamber Brick Work Completed

Phase - VI - Drainage Block Work Completed


Phase - VI - Individual Chamber Block Work Completed

Phase - VII - Compound Wall Painting Work in Progress

20th January 2012 Updation Schedule
Phase - 5- Road Concreting Work Completed



Phase - 5 - Site Marking Pole Fixing Work in Progress



Phase - 5 - Compound Wall Painting Work in Progress


Phase - 6- Road Soling Work in Progress



Phase - 6- Drainage Block Work Completed


Phase - 6- Manual Chamber Block Work Completed

Phase - 7- Compound Wall Painting Work in Progress


5th January 2012 Updation Schedule
Phase - 6 - Road Soling Work in Progress




Phase - 6 - Drainage Block Work Completed


Phase - 6 - Manual Chamber Brick Work Completed


Phase - 6- Individual Chamber Block Work Completed


Phase - 5- Road Concreting work Completed


Phase - 5- Site Marking Pole's Fixing Work in Progress



Phase - 5- Compound Wall Plastering Work in Progress


Phase - 7- Compound Wall Painting Work in Progress


|