15th January 2012 Updation Schedule
East Elevation

North Elevation

West Elevation

Block - C- Flooring Work in Progress

Block - C- Kitchen Work in Progress

Block - C- Internal Wall Putty Work in Progress


Block - C- Aluminum Window Frame Fixing Work in Progress

Block - C- Bathroom Tile Dadoing Work in Progress

Block - C- Door Frame Painting Work in Progress

Block - D- Aluminum French Window Frame Fixing work in Progress

Block - D- Internal Painting Work in Progress


Block - D- Aluminum Window Frame Fixing Work in Progress

Block - D- Internal Door Fixing Work in Progress

Block - D- Common Area Painting Work in Progress

Block - D- Flooring Work in Progress

15th December 2011 Updation Schedule
External View


Block - C- 2nd Floor Grill Painting Work in Progress

Block - C- 4th Floor Plumbing Work in Progress

Block - C- 5th Floor Electrical Switch Case Fixing Work in Progress

Block - C- 5th Floor Wall Putty Work in Progress


Block - C- 5th Floor Plumbing Work in Progress


Block - D- 1st Floor Window Aluminum Frame Fixing Work Completed

Block - D- 1st Floor Door Beading Fixing Work Completed

Block - D- 2nd Floor Door Fixing Work in Progress

Block - D- 3rd Floor Tiles Dadoing Work in Progress

Block - D- 6th Floor Flooring Work in Progress

Block - D- 6th Floor Tiles Dadoing Work in Progress

Block - D- 8th Floor Flooring Work in Progress

Block - D- Lift Scaffolding Work in Progress

15th November 2011 Updation Schedule
External View


C- Block - Wall Primer Putty Work in Progress


C- Block- Duct Plastering Work in Progress

C- Block - 8th Floor- Internal Plastering Work in Progress

D- Block- 2nd Floor - Granite Fixing Work in Progress

D- Block- 3rd Floor - Flooring Work in Progress

D-Block- 4th Floor - Internal Plumbing Work In Progress

D- Block- 5th Floor - Electrical Wiring Work in Progress

|